UPDATE - Testing at Guilford Reservoir Rescheduled to Begin March 16

Green banner with DPW logo and text "Department of Public Works Press Release"

The testing for the Guilford Reservoir project on West Cold Spring Lane, which had been set to begin Monday, March 13, 2017, was delayed by the predicted snowstorm and is instead being rescheduled to begin on Thursday, March 16. Testing is also anticipated on Friday, March 17, and will extend at least two days into the following week, March 20 and 21.

This series of Statnamic load tests involves the use of high pressure to assess the load-carrying capacity of deep foundations, and will create a loud but brief booming sound. An air horn will sound 30 minutes prior to each test as an alarm indicating the test is imminent. The test will not impact nearby properties, but could set off car alarms. There will be four tests in all over the several days, to be held between 10 a.m. and 3 p.m.

To view a Statnamic load test, please go to: https://www.youtube.com/watch?v=UPVuWBjAw2M.

The Guilford Reservoir project involves the placement of two buried 6.8 million gallon concrete water tanks within the footprint of the former open drinking water reservoir. New pumps, pump station, mains, drains, and site enhancements will be a part of the project. When completed, the extensive landscaping will create a very attractive green space in the Guilford Community.

There are four phases of the project:

Phase I – Construct bypass of the 48 inch water main. Completed

Phase II – Work on the reservoir itself, including draining it and installing tanks. This work is underway and will be completed by August 2018.

Phase III – Construction of the pump station and activation of the tanks. This phase will begin in June 2018 and be completed in one year.

Phase IV – Site restoration and landscaping. This is planned to begin in June 2019 and be done by November 2019.

Allen Myers, Inc. is the contractor for both the reservoir and pumping station. The total cost of this construction and renewal is approximately $75 million. This project is required by the Federal Clean Drinking Water Act in order to protect finished drinking water from the elements before it is sent to many of the 1.8 million customers of the Baltimore City water system.

Related Stories

The Department of Public Works is Now Accepting Public Comment on the Modified Sanitary Sewer Consent Decree Revised Operation and Maintenance Plan

The Modified Consent Decree Revised Operation and Maintenance (O&M) Plan has officially been released by the Baltimore City Department of Public Works (DPW) and is available on the DPW website for review and comment in accordance with the Modified Sanitary Sewer Consent Decree (MCD). DPW will accept public comments pertaining to this document for 30 days, through November 16, 2024Comments may be submitted directly to Michael.Shipman@baltimorecity.gov.

Baltimore City and County Submit Initial Water Service Line Inventory to MDE Part of a Nationwide Effort to Remove Lead Lines from Water Systems

On Tuesday, October 15, the Baltimore City Department of Public Works (DPW) and the Baltimore County Department of Public Works and Transportation (DPWT) submitted their initial water service line inventory to the Maryland Department of the Environment (MDE). This submission is part of a nationwide effort, led by the U.S. Environmental Protection Agency (EPA), to identify and eliminate lead and galvanized pipes from water distribution systems.

DPW is Now Accepting Public Comments on the Modified Sanitary Sewer Consent Decree Revised Emergency Response Plan 

The Baltimore City Department of Public Works (DPW)  has announced the release of its Revised Emergency Response Plan (ERP), a reference tool to be used by City personnel during a sanitary sewer overflow or reported building backup emergency. The Modified Sanitary Sewer Consent Decree (MCD) requires DPW to submit a revised Emergency Response Plan to protect the public health and welfare in the event of an unpermitted release, spill, or discharge of pollutants from the sewer collection system or in the event of a reported building backup.