Back River Project Moves Forward With New Construction Model

Green banner with DPW logo and text "Department of Public Works Press Release"

The Baltimore City Board of Estimates approved a contract Wednesday, May 4, that will allow work on the Headworks project at the Back River Wastewater Treatment Plant to proceed under an innovative, cost-saving model known as Construction Manager at Risk (CMAR).

The Headworks project is needed to alleviate a hydraulic restriction that keeps sewer water from efficiently entering the treatment plant. It causes a 10-mile-long backup in the sewer system that contributes to sewer overflows in the City, particularly following hard rains.

The Baltimore City Department of Public Works (DPW) turned to the CMAR model last year after bids to build the massive Headworks project ran more than $100 million over the estimated cost.

DPW officials are exploring the use of the CMAR model for other large infrastructure projects.

“I’m optimistic that by thinking creatively we will be able to deliver some of our projects for less money and in less time than what has become typical,” said DPW Director Rudy S. Chow, P.E. “We have billions of dollars in capital projects ahead of us, and we must continue to invest our ratepayers’ money wisely.”

A joint venture team of Clark Construction and Ulliman Schutte, LLC, won a contract for $3,839,000 to perform pre-construction services on the Back River project. The team was one of four that submitted proposals and were interviewed by members of DPW’s Office of Engineering and Construction. The Clark/Ulliman Schutte team was also approved by the Office of Boards and Commissions and the Architectural and Engineering Awards Commission.

The pre-construction process establishes the best way to perform what will be a multi-year build costing hundreds of millions of dollars. A guaranteed maximum price is also established in this early process in order to avoid cost overruns, and provides DPW with significant control over the process. The overall project schedule and cost is expected to be much less than with other construction models.

It is likely, under terms of the agreement, that the Clark/Ullimann Schutte joint venture will also be selected to perform the construction.

The Headworks project should be ready to move to construction by early next year. It is expected to be completed by the end of 2020.

Related Stories

Voluntary Water Restrictions Lifted for Baltimore Region Following Record Rainfall

Baltimore City DPW, in coordination with Baltimore County, Harford County, Howard County, and Carroll County, has lifted the voluntary water restrictions issued on May 8, 2025, for residents who are served by the local public water supply. The restrictions were initially implemented due to historically low water levels at Liberty Reservoir, one of the region’s primary drinking water sources.

DPW Offices and Sanitation Yards to Close for Juneteenth Holiday, Thursday, June 19 Trash and Recycling Rescheduled for Saturday, June 21

The Baltimore City Department of Public Works (DPW) Director Khalil Zaied reminds residents that Juneteenth will be observed on Thursday, June 19, 2025. As a City-observed holiday, DPW offices and sanitation yards will be CLOSED in observance of the holiday.  There will be NO trash or recycling collections on the Juneteenth holiday. The make-up collection day will be Saturday, June 21.

DPW Offices, Sanitation Yards Closed Memorial Day Holiday, Monday, May 26, 2025

The Baltimore City Department of Public Works (DPW) Director Khalil Zaied reminds residents that Memorial Day will be observed on Monday, May 26, 2025. As a City-observed holiday, DPW offices and sanitation yards will be CLOSED on that day. The Memorial Day closure will NOT impact weekly trash and recycling collections, as Monday is not a regularly scheduled curbside collection day. Mechanical street sweeping will be suspended on the holiday.