Board of Estimates Approves Quarter Billion Dollars for Wastewater Treatment Improvements

Green banner with DPW logo and text "Department of Public Works Press Release"

BALTIMORE MD (August 14, 2013) - Public Works Director Alfred H. Foxx today praised the approval, by the City’s Board of Estimates, of a $263.5 million contract for the first phase of construction of an Enhanced Nutrient Removal Facility (ENR) at the Back River Wastewater Treatment Plant. This contract was awarded to Archer Western Contractors, LLC, a leading firm in water, wastewater and transportation construction.

“This project is an integral part of the Chesapeake Bay Restoration Program mandated by the Maryland Department of the Environment,” said Mr. Foxx. “When completed, it will dramatically reduce the nutrients that contribute to algae blooms which reduce the oxygen content in the water and cause fish kills.”

The specific goal of this program is to reduce the nitrogen and phosphorus nutrient load to the Bay. These two elements are found in wastewater influent at all treatment plants. At Back River, approximately 35,000 lbs. of nitrogen and 6,000 lbs. of phosphorus enter every day in the influent wastewater.

The City of Baltimore owns and operates two of the largest wastewater treatment facilities in the State of Maryland. These are Back River at 8201 Eastern Boulevard, and Patapsco at 3501 Asiatic Avenue in Wagner’s Point. These plants, along with 65 others in the state, began nutrient reduction in the late 1990’s, targeting about 70% reduction of the incoming nitrogen using Biological Nutrient Removal (BNR) technology.

Under these new improvements, nitrogen will be cut by an additional 60% to achieve more than 90% total reduction. Chemical treatment of phosphorus at Back River has already resulted in removing 90% of it from the treated water.

This project, and a subsequent phase, will be a massive undertaking. It is estimated that 250 on-site construction jobs will be created under this contract alone. Many additional jobs will be provided to local off-site suppliers and support staff. It will have a considerable positive impact on the regional economy.

What is being constructed? :

Pumping Station (300 million gallon/day pumping capacity)

52 biological (“de-nitrification”) filters (each 100’Lx12’W)

Chemical feed facilities

Modifications to the existing Activated Plants 2 and 3

Supporting plant infrastructure including:

Underground utilities (piping, electrical, gas, communications)

Roadways

Communications and plant process control systems

40 MG biological (“nitrification”) reactor tankage (separate contract)

Twelve, 160-ft. diameter clarifier/ settling tanks (2 MG each) (separate contract).

All work will be completed on this and subsequent Back River ENR projects by December 2016. The vast majority of the funding for this work, 93.5%, comes from the State’s Bay Restoration Fee (Flush Tax). The other 6.5% of the cost is shared equally by Baltimore City and Baltimore County.

At the present time there are three projects under Construction for ENR work at the Patapsco Wastewater Treatment Plant. Two are nearing completion and the third will be finished by April 2015.

Director Foxx noted: “Growing Baltimore depends upon a healthy Chesapeake Bay. This work is not only an example of the City’s environmental and fiscal leadership, it is also an investment in our future.”

Related Stories

DPW to Start Trash and Recycling Collections at 5:00 a.m. During Summer Months Earlier Start Time Aims to Protect Workers from Extreme Heat –Seasonal Change Begins Tuesday, July 8

To protect sanitation workers from the dangers of extreme summer heat, the Baltimore City Department of Public Works (DPW) will begin trash and recycling collections one hour earlier—starting at 5:00 a.m.—beginning Tuesday, July 8. This seasonal adjustment will run through Tuesday, September 30, 2025.

DPW Offices and Sanitation Yards Closed for Independence Day

Baltimore City Department of Public Works (DPW) Director Khalil Zaied reminds residents that Friday, July 4, 2025, is Independence Day, a City holiday. As a result, all DPW offices and sanitation yards will be CLOSED in observance of the holiday. There will be no trash or recycling collections on Friday, July 4. Collections will resume on the makeup day, Saturday, July 5, 2025. Additionally, there will be no street sweeping due to the holiday closure.

DPW Releases 2024 Water Quality Report

The Baltimore City Department of Public Works (DPW) today announced the release of its 2024 Water Quality Report, providing residents in Baltimore City and Baltimore County with important information about the quality of their drinking water.